Construcción Laguna Crystal - Hernandarias.
Client: RAICES S.A. Period: 2019. Main jobs executed: Artificial lake with two wager mirrors at uneven level. Depth: 2m. 134,000 m3 Ground Movement.
Ampliación y profundización de la toma de agua del Río Pilcomayo
Client: Ministry of Public Works and communications. Period: 2012– 2016. Main jobs executed: Channel Digging and shaping. Bridges and sewers. Rural roads.
Mejora y Rehabilitación de la Defensa Costera de la Ciudad de Concepción Primera Etapa
Client: MINISTRY OF PUBLIC WORKS AND COMMUNICATIONS. Period: 2001 – 2003. Main works executed: Filling and compacting. Slope casting, placement, and material. Soil excavation. Removal of existing dam. Installation of reinforced concrete pipes. Raw stone wall.
Construcción de aductores, centros de distribución y estaciones de bombeo en el Chaco Central - Fase II
Construction of both adductor, distribution centers and pumping stations in the Central Chaco – Phase II –Program of Sanitation and drinking water for tChaco and intermediate cities of the eastern region of Paraguay, 2589/BL-PR GTR/WS-12928-Pr. Client: Ministry of Public Works and communications (MOPC). Period: 2017 to 2019. Main jobs executed: Distribution Center at Loma Plata. […]